News

This section will show news and updates about the IMPACTA project and activities of the consortium members in relation to IMPACTA.


  • No categories

consortium meets for 1st review meeting (pre-PDR) – 10/2019

The third face to face meeting of IMPACTA was done at the end of October in Grenoble, France. Representatives of all companies part of the consortium were present, as well as the Project Officer assigned to the project from the European Commission.

At the beginning, a quick overview of the project was done by the Project Manager in order to update the schedule due to the extension of 6 months granted by the EC. The meeting followed discussing about tasks involved in WP3 and advances with each of the tasks. Participants will continue working on their tasks and update the rest of the consortium every two weeks on the Progress Meetings scheduled.


SRR meeting in toulouse – 05/2019

The SRR meeting took place at Airbus offices in Toulouse (France) the 15th of May. Participants of all companies attended and the main objective of the meeting was the preparation of WP3.

WP1: Technical and Project Management was updated and then tasks to prepare for WP3 were reviewed with each task responsible. At the end of the meeting, 16 actions to be done were highlighted for the consortium to continue working on IMPACTA and progress adequately to deliver WP3.


PROGRESS MEETINGS

After the kick-off meeting, IMPACTA consortium decided to meet once every two weeks in order to keep track of the progress of the project and update the rest of the members about the activities carried out and discuss decisions to be taken and possible problems that may arise.


IMPACTA KICKS OFF! – 01/2019

IMPACTA kicked off with the start of 2019. In January, the first official meeting of Impacta was held in Spain. The Consortium met in AVS’s Headquarters in the town of Elgoibar to officially meet the rest of the colleagues of the consortium and to set the procedures and working lines of IMPACTA.

The agenda of the day covered a presentation of the participant companies and the team, and was followed by a review of the technical objectives, the project timeline and the project management methodology. Each Work Package (WP) was presented with objectives, tasks and associated deliverables.

The kick-off concluded with a recap of the actions to be done for the following meeting and a visit to AVS’s facilities.